Language selection

Search


Top of page

Departmental Results Report - Supplementary Information Tables

Alternative formats

Table of Contents

Details on Transfer Payment Programs of $5 Million or More

Details on the Contributions under the Canada/European Space Agency (ESA) Cooperation Agreement.
Name of transfer payment program Contributions under the Canada/European Space Agency (ESA) Cooperation Agreement.
Start date
  • (ratification of the current Agreement);
  • (approval of the revised Terms and Conditions)
  • (approval of revised Terms and Conditions)
End date (end date of the latest Agreement).
Type of transfer payment Contribution
Type of appropriation Annually through Estimates.
Fiscal year for terms and conditions The current revised Terms and Conditions for the contributions, under the Cooperation Agreement, were approved in .
Strategic Outcome Canada's exploration of space, provision of space services and development of its space capacity meet the nation's needs for scientific knowledge, innovation and information.
Link to department's Program Alignment Architecture
  • Program 1.3 Future Canadian Space Capacity
  • Sub-Program 1.3.2 Space Innovation and Market Access
  • Sub-Sub-Program 1.3.2.1 International Market Access
Description Enhance Canadian industry's technological base and provide access to European markets for value-added products and services in the fields of Earth observation (EO), telecommunications and generic technological activities; foster the participation of Canadian academia and make possible the demonstration of Canadian space technologies in European microgravity and space exploration missions and programs. This is achieved through a financial contribution by the CSA to ESA optional programs.
Results achieved

For the period of , to , Canada achieved a return coefficient of 106%, which is much higher than the minimum guaranteed to ESA member states (i.e. 91% at end of ) and the ideal value (i.e. 100%). This coefficient indicates that as a result of the Canada-ESA Agreement, Canada is successful in obtaining its fair share of ESA contracts although the period for the statistics is short.

Through Canada's participation in ESA Earth Observation programs, more specifically the Earth Observation Envelope Program, Copernicus Space Component, and European Earth Watch, the CSA has continued to support Canadian companies with the development of advanced space-borne instruments and subsystems and user-oriented applications, and to ensure access to the data for Canadians. In the spring of , Canada announced a new subscription of $6.5M (€4.2M) in the European Earth Watch for the Climate Change Initiative (CCI+) and the ALTIUS mission elements. Canadian scientific teams were awarded contracts under the CCI+ element to work on three new Environment Climate Variables, namely Lakes, Snow and Water Vapour. The Canadian mission ePoP has been successfully incorporated as the fourth satellite of the ESA Swarm constellation, whose objective is to make precise measurements of Earth's magnetic field. It allowed the ePoP mission three additional years of instrument operation and data collection, and it enabled a close collaboration of Canadian scientists with the European counterparts in the area of ionospheric research. The firm Communication & Power Industries LLC continued the work to supply the Klystron High Power Amplifier for Wind Scatterometer Instrument on MetOp-Second Generation satellites, the first of which is scheduled for launch in .

The CSA has supported the development and demonstration of innovative space technologies through its participation in ESA's General Space Technology Program. For example, Neptec Design Group and NGC Aerospace will be providing critical technologies for the formation flying mission Proba 3, to be launched at the end of . NGC Aerospace is also involved in the development of vision-based navigation algorithms for precise landing on the Moon and Mars.

Through its partnership with ESA, the CSA has continued to position the Canadian industry and scientists in future scientific and technological developments related to the Aurora planetary exploration programs, the European Life and Physical Science (ELIPS) Program, and the new European Exploration Envelop Program (E3P). The E3P is taking over activities previously covered by ELIPS and Aurora, in order to integrate ESA's space exploration efforts into one program. Under the Aurora Program, MDA and Neptec Design Group continued the significant development of their respective rover subsystems as part of the second of two ExoMars missions, which is planned for launch in . In the spring of , Canada announced new subscriptions of $8.1M (€5.25M) in Aurora and $7M (€4.5M) in E3P, in order to secure Canadian industry's participation in the European space exploration program.

Canada's participation in the European Advanced Research in Telecommunications Systems (ARTES) has continued to allow our industry to access forward-looking studies on new telecommunications services, and to develop new satellites, technologies, equipment and applications. The additional contribution to ARTES made at the ESA Council meeting at Ministerial level, which included a supplementary $30M announced in Budget for that program, resulted in many important contracts to Canadian industry. For example, MacDonald, Dettwiler and Associates (MDA) is developing and providing antennas for the OneWeb megaconstellation and is also involved in the European Data Relay System (EDRS) Global project, a public private partnership with ESA and Airbus. Other examples include Honeywell's development on Q/V Band High Power Devices, MPB's SMART Optical Amplifier for the European TESAT satellite supplier, Optelian's Optical Polarization Modulator development and Xiphos Technology providing major subsystems for the IODA platform.

Finally, Canada joined the new Navigation Innovation and Support Program (NAVISP) in the spring with a subscription of $3.1M (€2.0M). It will provide Canadian companies with the opportunity to bid on tenders as part of this program.

Comments on variances The variance of $5.1 million is due to the increase in payments, in accordance with the budgetary feasibility principle governing member states' and Canada's contributions to ESA, against Canada's binding multiyear legal obligations with respect to its participation in ESA optional programs.
Audits completed or planned N/A
Evaluations completed or planned The program evaluation covering the period from to was completed and approved by the President on . A program evaluation covering the period from , to , began in and is expected to be completed in . The results of this evaluation will complement the evaluations undertaken in and .
Engagement of applicants and recipients The CSA actively consulted the Canadian space sector (i.e. both industry and academia) and Government of Canada (GoC) organizations as part of the program selection process in preparation for the ESA Ministerial Council meeting during which ESA member states and Canada announced their position on contributions to the proposed ESA Programs. Similar consultations are planned for the ESA Ministerial Council meeting planned for .

Performance Information (dollars)

Contributions under the Canada/European Space Agency (ESA) Cooperation Agreement.
Type of Transfer payment Actual
spending
Actual
spending
Planned
spending
Total
authorities available for use
Actual
spending (authorities used)
Variance ( actual minus planned)
Total contributions 27,802,596 34,498,797 36,648,000 41,766,523 41,766,413 5,118,413
Total program 27,802,596 34,498,797 36,648,000 41,766,523 41,766,413 5,118,413
Details on the Class Grant and Contribution Program to Support Research, Awareness and Learning in Space Science and Technology.
Name of transfer payment program Class Grant and Contribution Program to Support Research, Awareness and Learning in Space Science and Technology.
Start date
End date N/A – Ongoing program
Type of transfer payment Grant and Contribution
Type of appropriation Annually through Estimates
Fiscal year for terms and conditions
Strategic Outcome Canada's exploration of space, provision of space services and development of its space capacity meet the nation's needs for scientific knowledge, innovation and information.
Link to department's Program Alignment Architecture

Program 1.1 Space Data, Information and Services

  • Sub-Program 1.1.1 Earth Orbit Satellite Missions and Technology
  • Sub-Sub-Program 1.1.1.3 Scientific Missions
  • Sub-Program 1.1.2 Ground Infrastructure
  • Sub-Sub-Program 1.1.2.2 Data Handling
  • Sub-Program 1.1.3 Space Data, Imagery and Services Utilization Development
  • Sub-Sub-Program 1.1.3.1 Earth Observation Data and Imagery Utilization

Program 1.2 Space Exploration

  • Sub-Program 1.2.1 International Space Station
  • Sub-Sub-Program 1.2.1.2 International Space Station Utilization
  • Sub-Program 1.2.2 Exploration Missions and Technology
  • Sub-Sub-Program 1.2.2.1 Space Astronomy Missions
  • Sub-Program 1.2.3 Human Space Missions and Support
  • Sub-Sub-Program 1.2.3.3 Health and Life Sciences

Program 1.3 Future Canadian Space Capacity Program

  • Sub-Program 1.3.1 Space Expertise and Proficiency
  • Sub-Program 1.3.2 Space Innovation and Market Access
  • Sub-Sub-Program 1.3.2.2 Enabling Technology Development
Description

This program supports knowledge development and innovation in the CSA's priority areas while increasing the awareness and participation of Canadians in space-related disciplines and activities. The program has two components:

  1. Research
  2. Awareness and Learning

The Research component aims to support the development of science and technology; foster the continual development of a critical mass of researchers and highly qualified people in Canada; and support information gathering and space-related studies and research pertaining to Canadian Space Agency priorities.

The Awareness and Learning component aims to provide learning opportunities to Canadian students in various space-related disciplines; to support the operations of organizations dedicated to space research and education; and to increase awareness of Canadian space science and technology among Canadian students and their participation in related activities.

Results achieved

In , Canadian universities and for-profit and not-for-profit organizations established and operating in Canada made significant contributions to knowledge creation in space science and technology priority areas through 11 new Announcements of Opportunity (AOs) posted on the CSA's website, resulting in 100 new supported research projects. For more information regarding these initiatives consult the Programs Results Section of the DRR.

Global Results: The annual Web-based follow-up project survey showed results of 506 publications among which 75% were peer reviewed and 1052 presentations among which 158 were presentations on making space science and technology more readily understandable for the general public and 217 other outreach / general scientific awareness activities. 1772 research team members were involved in the supported initiatives representing 600 persons per year in terms of Full-Time Equivalents (FTE). From these Highly Qualified Personnel (HQP), 443 were faculty members, 595 were students and post-doctoral fellows and 265 were technicians and other research team members.

A total of 213 research organizations have been involved in the funded projects (i.e. 60% universities, 17% foreign research organizations, 16% private sector and 7% other). 69% of research partners are international and 31% are national.

Comments on variances

Grants: Due to delays in granting agreements, some of the expenditures planned for will be incurred in .

Contributions: The variance is mainly due to the decreased expenditures resulting from delays in Space Technology Development projects.

Audits completed or planned - planned
Evaluations completed or planned - planned
Engagement of applicants and recipients

Since , an initiative to engage recipients has been undertaken through an automated annual follow-up of projects. The Agency has extended this initiative in order to establish a dialogue with potential applicants and recipients.

Consultations, presentations to, and discussions with, the academic and industrial communities as well with other potential recipient groups, are ongoing and will continue.

Performance Information (dollars)

Class Grant and Contribution Program to Support Research, Awareness and Learning in Space Science and Technology
Type of Transfer payment Actual
spending
Actual
spending
Planned
spending
Total
authorities available for use
Actual
spending (authorities used)
Variance ( actual minus planned)
Total contributions 6,263,510 9,146,442 13,001,000 10,523,859 10,507,215 (2,493,785)
Total other types of transfer payments 10,501,603 11,870,329 11,317,000 8,675,618 8,674,322 (2,642,678)
Total program 16,765,113 21,016,771 24,318,000 19,199,477 19,181,537 (5,136,463)

Fees

Owing to legislative changes, the to fees results will be published in a separate report. The Fees Report is currently under development, and the link to the Fees Report, once tabled in Parliament, will appear on this web page by .

Evaluations

Evaluations completed, or planned to be completed, in
Title of evaluation Link to the department's Program Alignment Architecture Status on Deputy head approval date*
Evaluation of the Earth Observation Business Line of the Canadian Space Agency
  • 1.1.1.1. Earth Observation Missions
  • 1.1.2. Ground Infrastructure
  • 1.1.3.1 Earth Observation Data and Imagery Utilization
Completed
Evaluation of the Canadian Space Agency Space Expertise and Proficiency Sub-Program
  • 1.3.1. Space Expertise and Proficiency
Completed
Evaluation of the Space Astronomy Missions and Planetary Missions Programs
  • 1.2.2.1. Space Astronomy Missions
  • 1.2.2.2. Planetary Missions
Completed

Internal audits

Internal audit engagements completed in
Title of internal audit Completion date
Audit of the Management Framework of the Canadian Space Agency's Ground Infrastructure Subprogram
Audit of the Management Framework of the Canadian Space Agency's Space Astronomy and Planetary Missions Program

Response to parliamentary committees and external audits

Response to parliamentary committees

There were no parliamentary committee reports requiring a response in .

Response to audits conducted by the Office of the Auditor General of Canada (including audits conducted by the Commissioner of the Environment and Sustainable Development)

There were no recommendations for the Canadian Space Agency.

Response to audits conducted by the Public Service Commission of Canada or the Office of the Commissioner of Official Languages

There were no recommendations for the Canadian Space Agency.

Status report on projects operating with specific Treasury Board approval

Status report on projects operating with specific Treasury Board approval details
Project name and
project phase
Original estimated total cost
(dollars)
Revised estimated total cost
(dollars)
Actual total cost
(dollars)
Main Estimates
(dollars)
Planned spending
(dollars)
Total authorities
(dollars)
Actual spending
(dollars)
Expected date of close-out
1.1 Space Data, Information and Services
RADARSAT-Constellation MCP EPA 600,000,000 1,089,510,532 988,660,771 67,079,896 83,705,095 87,032,828 75,640,928 -
Maritime Monitoring and Messaging Microsatellite (M3MSat) EPA 5,404,000 16,653,419 15,274,488 0 0 65,410 65,373 -
Surface Water & Ocean Topography (SWOT-C) 8,496,507 9,963,696 4,878,040 1,824,905 2,095,905 2,438,843 857,424 -
1.2 Space Exploration
OSIRIS-REx Laser Altimeter (OLA) EPA 26,696,400 35,760,462 35,760,462 0 48,000 63,156 63,156 -
James Webb Space Telescope MCP (JWST) EPA 67,160,000 172,860,953 169,213,011 1,315,325 1,870,871 2,300,239 1,384,686 -
Mobile Servicing System Replacement Camera (MSS RCAM) 15,465,270 19,145,825 16,466,228 2,339,100 2,339,100 1,283,109 1,274,103 -
Dextre Deployable Vision System (DDVS) 23,351,302 22,126,990 6,196,110 8,080,817 9,455,817 7,793,690 3,560,998 -
Life Science Research System (LSRS) 15,268,161 16,748,151 12,579,731 6,476,059 7,790,843 7,788,005 7,097,176 -
1.4 Internal Services
David Florida Laboratory Infrastructure Accelerated Refit (DFL-IAR) 12,022,802 13,544,547 9,525,016 4,365,000 7,811,805 8,630,713 6,170,091 -

Note: dollar amounts exclude both the goods and services tax (GST) and the harmonized sales tax (HST).

Status report on transformational and major Crown projects

General information

RADARSAT Constellation Mission general information
Project name RADARSAT Constellation Mission (RCM)
Description

The RADARSAT Constellation Mission (RCM) is the next generation of Canadian Earth observation (EO) radar satellites. RADARSAT-1 was launched in and continued its operation until . RADARSAT-2, developed by the private sector in partnership with the Government of Canada (GoC), was launched in for a seven-year mission, but given its current performance, it is expected to remain operational for several more years. Canada has established itself as a leading global supplier of C-band satellite radar data for EO. The successor mission to RADARSAT-2, the RCM will maintain the leadership and position of Canadian industry in space radar technology and value-added product markets.

The RCM is comprised of three identical satellites. The launch of the constellation is planned for . With a constellation, the time between successive imaging of a specific point on Earth is significantly reduced from 24 to four days. The creation of a three-satellite constellation will increase the frequency of available information, as well as the reliability of the system, making it better suited to the requirements of operations of both public and private users.

The scope of the RCM Major Crown Project includes the requirement definition, design, development, manufacturing, integration, testing and launch of the satellites as well as the design, development, manufacturing and installation of the associated ground segment. One year of operation of the three-satellite constellation is also included as well as an application development program.

The RCM will provide reliable data in all weather and illumination conditions in support of federal departments' operations and mandates in areas such as maritime surveillance, disaster management, environmental monitoring and natural resource management. The satellite constellation will provide average daily coverage capacity of most of Canada and its surrounding waters. In the North, the constellation will provide two to three times daily coverage capacity of the Arctic and the Northwest Passage.

In support of the maritime surveillance requirements of federal departments, the RCM is the principal data source envisaged for wide-area surveillance of Canada's remote areas and marine approaches. Only satellite data can offer regular cost-effective information to task ships and aircraft in order to intercept suspicious vessels.

The daily coverage of marine areas will also support fisheries monitoring, ice and icebergs monitoring, pollution monitoring, and integrated ocean and coastal zone management. The RCM's maritime surveillance capabilities also support Canadian sovereignty and security. The RCM satellites will be able to capture ship-originated Automatic Identification System (AIS) signals from space. The combination of space-based radar images and AIS signals will provide a powerful surveillance capacity over Canada's maritime approaches and elsewhere in the world.

In support of disaster management, both in Canada and around the world, the RCM will provide critical and timely data to support disaster mitigation, warning, and response and recovery activities, while helping Canada meet its obligations with respect to international disaster relief. The types of disasters for which RCM data will be used for monitoring and relief purposes include floods, oil spills, volcanic eruptions, earthquakes and hurricanes.

In support of environmental monitoring, the RCM will provide data for wide-area change detection in order to provide support for activities such as water monitoring, wetlands mapping, coastal change monitoring and changes in the permafrost in northern Canada. RCM data will contribute to the production of more accurate weather forecasts and warnings pertaining to marine conditions, winds, severe storms and floods.

In support of natural resource management, RCM data will be a critical source of information to monitor the changing state of Canada's agricultural areas, forests and wildlife habitats. RCM data will also be used in the mining and energy sectors for resource exploration operations to ensure that critical infrastructure is monitored properly for safety and integrity.

In addition, the RCM will sustain the development of Canadian high-technology design and manufacturing capabilities and the integration of satellite data into information products and services. Canada's space and geomatics industries will benefit from better positioning in international markets and privileged access to data deemed essential by many international users.

Project outcomes

This Major Crown Project (MCP) contributes to Program 1.1 Space Data, Information and Services, which includes the provision of space-based solutions and the progression of their utilization. It also serves to install and run ground infrastructure that processes the data and operates satellites. This Program utilizes space-based solutions to assist Government of Canada (GoC) organizations in delivering growing, diversified and cost-effective programs and services within the purview of their respective mandates, each related to key national priorities such as sovereignty, defence, safety and security, resource management, environmental monitoring and the North. It also provides academia with data required to perform its own research. The contribution of the MCP to the program objectives is measured through the Performance Measurement Framework (PMF) (i.e. Program Alignment Architecture (PAA) results and performance indicators).

Program 1.1 Space Data, Information and Services

Result: Government of Canada (GoC) organizations offer more diversified or cost-effective programs and services due to their utilization of space-based solutions.

Performance Indicator #1: Number of new GoCs programs offering more diversified or efficient services.

Sub-Program 1.1.1 Earth Orbit Satellite Missions and Technology

Result: GoC organizations are using space-based data to deliver their mandate.

Performance Indicator #1: Number of GoC programs using space data or derived information to deliver their mandate.

Performance Indicator #2: Percentage of RADARSAT data used in program delivery.

Industrial benefits

The RCM is expected to generate significant industrial benefits in the space and Earth Observation sectors, such as employment, economic growth and improved productivity. Investments in RCM also support the growth of small and medium-sized companies as well as Canadian capabilities in terms of infrastructure and services.

The prime contract includes a requirement for 70% Canadian content, excluding launch services and subsystems for which there are no suppliers available in Canada. As of (the latest date for which data is available) this corresponds to a Canadian content requirement of $485.2 million. For the same period, the CSA had provided the Canadian industry with funding of more than $575.3 million to carry out work resulting directly from the design of the RCM MCP, thus surpassing the requirement.

The prime contract also requires that 3.5% of the 70% Canadian content be subcontracted in the Atlantic Canada region. For the same period, the actual Atlantic Canadian content was $22.6 million, considerably higher than the requirement of $17.0 million.

The prime contract includes reporting obligations and performance measurements as well as financial penalties for not meeting the minimum Atlantic Canada content requirement.

Sponsoring department Canadian Space Agency (CSA)
Contracting authority Public Services and Procurement Canada (PSPC)
Participating departments
  • Agriculture and Agri-Food Canada
  • Canadian Coast Guard
  • Environment and Climate Change Canada
    • Canadian Ice Service
  • Fisheries and Oceans Canada
  • Global Affairs Canada
  • Indigenous and Northern Affairs Canada
  • Innovation, Science and Economic Development Canada
  • National Defence and the Canadian Armed Forces
  • Natural Resources Canada
  • Parks Canada
  • Public Safety Canada
  • Royal Canadian Mounted Police
  • Statistics Canada
  • Transport Canada
Prime contractor MDA Systems Ltd. (a division of MacDonald, Dettwiler and Associates), Richmond, British Columbia
Major subcontractors

Tier 1 Major Subcontractors:

  • MDA Montreal, Ste-Anne-de-Bellevue, Quebec
  • Magellan Aerospace, Winnipeg, Manitoba
  • MDA, Halifax, Nova Scotia
  • SpaceX, Hawthorne, California, USA
  • Airbus Defence and Space, United Kingdom
  • Honeywell Aerospace, United Kingdom

Tier 2 and Tier 3 Canadian Subcontractors:

  • Stelia Aerospace North America, Lunenburg, Nova Scotia
  • IMP Group, Halifax, Nova Scotia
  • DRS, Ottawa, Ontario
  • Mecachrome, Mirabel, Quebec
  • Maya, Montreal, Quebec
Project phase Phase D – Implementation
Major milestones
  • Phase A: Requirement Definition ()
  • Phase B: Preliminary Design ()
  • Phase C: Detailed Design Review ()
  • Phase D: Launch satellite #1, #2, and #3 ()
  • Phase E1: Operations (part of MCP) ()
  • Phase E2: Operations (not part of MCP) ()
Progress report and explanation of variances

On , the Domestic Affairs Committee of Cabinet granted approval-in-principle to a 10-year program to implement a RADARSAT Constellation Mission (RCM) aimed at addressing the operational needs of users from the public and private sectors in relation to Canadian sovereignty and marine surveillance, environmental monitoring and change detection, and disaster management. The RCM would be government-owned and operated.

On , Treasury Board granted Preliminary Project Approval (PPA) for the RCM and expenditure authority for the Project Initial Planning and Identification (i.e. Phase A). During Phase A, feasibility studies were completed, user requirements were defined, and risk mitigation activities and options analysis for the bus and payload were carried out. The initial scope of work for Phase A was completed in . Phase A was then extended to allow additional technical risk reduction activities to continue during the period prior to the Phase B contract award. This was completed in .

In , Treasury Board approved a revised PPA submission to proceed to Phases B and C. Following a competitive Request for Proposal (RFP) process, PWGSC obtained authority to enter into negotiations with MDA, the prime contractor, and awarded the contract for Phase B in . The Preliminary Design (i.e. Phase B) was completed in . The contract for Phase B was subsequently amended to include the detailed design (i.e. Phase C).

A second revised PPA was approved by Treasury Board in . The purpose of this revised PPA was to provide additional expenditure authority to include the procurement of long-lead items during Phase C and also to include a technology demonstration for Automatic Identification System (AIS) payloads, funded by the National Defence.

The final review of the overall mission-level system detailed design, the Mission Critical Design Review (CDR), was conducted in . A selected set of activities, such as completing the design qualification activities and the procurement of long-lead items, pursued under Phase C were completed in . These selected activities were scheduled to be completed in but were delayed due to technical difficulties encountered during the building of the qualification models. The delay has no impact on the project.

Treasury Board granted Effective Project Approval for the RCM in , which provides expenditure and contracting authorities to complete the project and carry out the first year of RCM operations (Phases D and E1). The contract was awarded on . Since contract award, planning activities were completed and major milestones achieved to initiate the implementation phase of the satellites and associated ground system.

In , a Deputy Ministers' Governance Committee (DMGC) was established to provide oversight, coordination and accountability on the RCM MCP. The DMGC reports to the Minister of Innovation, Science and Economic Development and provides strategic direction while making timely decisions to address issues and risks that could affect the success of the MCP.

Significant progress continued in the manufacturing of the RCM satellites throughout . Assembly, integration and testing of the last of the three synthetic aperture radar (SAR) and automatic identification system (AIS) payloads were completed, and the payloads were delivered. Challenges in completing the flight software were addressed. Assembly and integration of the first satellite were completed, and its testing is well underway. Assembly, integration and testing of the second satellite have started. Assembly, integration and testing of the third satellite will start once the third satellite bus is completed and delivered early in . Three of the eight ground segment subsystems were completed. Upgrades to the CSA headquarters in Saint-Hubert to accommodate the RCM ground segment also progressed significantly. The launch dispenser was completed and, as the scheduled launch date approaches, the period of the launch event was narrowed from twelve months to three months (, to ).

Significant progress continued in the manufacturing of the RCM satellites throughout . Assembly, integration and testing of the last satellite bus was completed and delivered. The three satellites have progressed to a state of completion of 87%, 61% and 41% respectively. All of the ground segment subsystems were delivered to and integrated into the Primary Control Facility in Saint-Hubert, Quebec. Upgrades to the CSA headquarters in Saint-Hubert to accommodate the RCM ground segment were also completed in time for the arrival of the ground segment subsystems. Significant progress was also achieved in finalizing the Data Policy. A provisional Operating Licence was issued by Global Affairs Canada. The period of the launch event was narrowed from three months to 30 days (, to ).

James Webb Space Telescope general information
Project name James Webb Space Telescope
Description

The James Webb Space Telescope is a joint international mission involving National Aeronautics and Space Administration (NASA), the European Space Agency (ESA) and the Canadian Space Agency (CSA). The mission concept is for a large field-aperture telescope to be located 1.5 million km from Earth. Like Hubble, the James Webb telescope will be used by the astronomy community to observe targets ranging from objects within our solar system to the most remote galaxies which can be seen during their formation in the early universe. The science mission is centred on the quest to understand our origins:

  • Observing the very first generation of stars to illuminate the dark universe when it was less than one billion years old;
  • Understanding the physical processes that have controlled the evolution of galaxies over cosmic time and, in particular, identifying the processes that led to the assembly of galaxies within the first four billion years after the Big Bang;
  • Understanding the physical processes that control the formation and early evolution of stars in our own and other nearby galaxies; and
  • Studying the formation and early evolution of proto-planetary disks, and characterizing the atmospheres of isolated planetary mass objects.

The James Webb telescope is currently planned to launch in . James Webb instruments will be designed to work primarily in the infrared range of the electromagnetic spectrum, with some capability in the visible range. The James Webb telescope will have a large mirror, 6.5 metres in diameter and a sun shield that will be the size of a tennis court once deployed in outer space.

Canada is providing the Fine Guidance Sensor (FGS) and the Near-Infra-Red Imager and Slitless Spectrometer (NIRISS). The FGS is integral to the attitude control system of the James Webb telescope, and consists of two fully redundant cameras that will report precise pointing information. Canadian expertise in this area was established previously with the successful fine error sensors for the former Far Ultraviolet Spectroscopic Explorer (FUSE) mission. Packaged with the FGS but functionally independent, the NIRISS covers the 0.7 to 5 micrometer spectral range. NIRISS provides a specialized capability for surveys of objects such as primeval galaxies, for the study of transiting planetary systems and for high-contrast imaging applications such as the detection of extra-solar planets. 

With COM DEV Canada as the prime contractor, the James Webb Space Telescope-FGS Major Crown Project consists of the design, development, testing and integration into the spacecraft, launching and commissioning of the FGS and NIRISS. By participating in this leading-edge international space exploration mission, the CSA is actively promoting Canadian scientific expertise and innovative, advanced space technologies.

The National Research Council's Herzberg Astronomy and Astrophysics (NRC Herzberg) is a key Government of Canada (GoC) partner for activities related to the development of science instruments and distribution of telescope data. In return for its overall investment in the James Webb telescope, Canada will obtain a minimum of 5% of the time on this unique space telescope.

Already, the news of Canada's involvement in this international space exploration mission is inspiring youth, educators and amateur astronomers, and rallying members of Canada's world-renowned astrophysics community.

Project outcomes

This MCP contributes to Program 1.2 Space Exploration which provides valuable Canadian science, signature technologies and qualified astronauts to international space exploration endeavours. It fosters the generation of knowledge as well as technological spin-offs that contribute to a higher quality of life for Canadians. This Program appeals to the science and technology communities. It is targeted mostly towards Canadian academia and international space exploration partnerships. Canadian industry also benefits from the work generated within this Program. The contribution of the MCP to the program objectives is measured through the Performance Measurement Framework (PMF) (Program Alignment Architecture (PAA) results and performance indicators).

Program 1.2 Space Exploration

Result #1: Expansion of advanced scientific knowledge acquired through space exploration endeavours.

Performance Indicator #1: Number of peer-reviewed scientific publications, reports and conference proceedings using space exploration information and produced by researchers (sciences and technologies) in Canada.

Result #2: Multiple use and applications of knowledge and know-how acquired through space exploration endeavours.

Performance Indicator #1: Number of terrestrial applications of knowledge and know-how acquired through space exploration endeavours.

Performance Indicator #2: Number of space re-utilizations of knowledge and know-how acquired through space exploration endeavours.

Sub-Program 1.2.2 Exploration Missions and Technology

Result #1: Technological know-how is acquired through Space Exploration endeavours (Astronomy and Planetary).

Performance Indicator #1: Proportion of the CSA missions/solutions/instruments that met their mission performance requirements at acceptance review and/or at commissioning.

Result #2: Canada maintains a strategic positioning which supports its capacity to influence space exploration missions and decision-making processes in key international space exploration forums.

Performance Indicator #1: Number of CSA sponsored highly qualified personnel (HQP) nominated on the International Space Exploration decision bodies.

Result #3: CSA's participation in space exploration missions provides access to scientific data about the Solar System and the Universe.

Performance Indicator #1: Number of CSA's sponsored space astronomy and planetary missions providing data to Canadian scientific community.

Industrial benefits Most of the direct industrial benefits from the construction of the Webb-FGS and NIRISS system will accrue to Ontario.
Sponsoring department Canadian Space Agency (CSA)
Contracting authority Public Services and Procurement Canada (PSPC)
Participating departments
  • NRC Herzberg Astronomy and Astrophysics
  • Innovation, Science and Economic Development (ISED)
Prime contractor
  • Honeywell Aerospace, Ottawa, Ontario
Major subcontractors
  • Teledyne, USA
  • Corning Netoptix, USA
  • IMP Aerospace Avionics, Canada
  • ABB Bomem, Canada
  • MDA, Canada
  • INO, Canada
  • BMV, Canada
  • CDA Intercorp, USA
  • ESTL, Europe
  • Bach Research Corporation, USA
  • Materion, USA
  • Camcor, Canada
Project phase Phase D – Implementation
Major milestones
  • Phase A: Requirement Definition ()
  • Phase B: Preliminary Design ()
  • Phase C: Detailed Design ()
  • Phase D: Manufacturing/Assembly, Integration/Testing, Pre-launch preparations, Launch/System Commissioning ()
  • Phase E: Operations (part of MCP) ()
Progress report and explanation of variances

In , Treasury Board granted Preliminary Project Approval for Phases B, C and D. In , before the completion of Phase C, detailed design of the FGS, the CSA requested increased expenditure authority to complete the project. In , the Treasury Board granted Effective Project Approval (EPA) and the project became a Major Crown Project (MCP).

In , the first Critical Design Review (CDR) for the guidance function of the FGS revealed technical issues. During the preparation of the system-level CDR, new issues became apparent. The technical issues needed to be addressed.

In , Treasury Board granted a revised EPA after project costs had raised significantly due to technical issues by the end of Phase C, the detailed design phase.

In , NASA discovered that the infrared detectors, extremely sensitive cameras capable of "seeing" light produced by heat, were showing signs of performance degradation due to a design fault. Following investigation, NASA concluded that all detectors, including the four procured by Canada, needed to be replaced. In effect, two years after their acceptance by the project, the detectors started to show the same degradation. NASA initiated an improvement project with Teledyne Scientific & Imaging LLC to address the design issue causing the degradation.

In , work continued on hardware and software development. COMDEV Canada worked on the Proto Flight Model (PFM) which successfully completed a very stringent environmental test campaign during which the instrument was subjected to cryogenic temperatures over a period of 80 continuous days. Teledyne Scientific & Imaging LLC completed the detector design improvements and, pursuant to testing successfully addressed the degradation issues. NASA then initiated the procurement process for new detectors for the James Webb telescope Mission; the acquisition of the detectors for the FGS/NIRISS was under the responsibility of the CSA.

The FGS Engineering Test Unit (ETU) was integrated into the NASA Goddard Space Flight Center (GSFC) test set-up and underwent system-level testing with the other science instrument engineering units. The integration test onto the Integrated Science Instrument Module (ISIM) of the James Webb telescope was successfully conducted. A technical issue surfaced with a component, the Tunable Filter Instrument (TFI), which triggered the need for a change in the design approach and led to the design and development of the Near-Infrared Imager and Slitless Spectrograph (NIRISS). This new instrument relied on existing components of the old TFI but used a different approach to cover the light spectrum required for the science mission.

On , the PFM FGS/NIRISS was delivered to NASA GSFC. On , the PFM FGS/NIRISS was officially accepted by NASA following the successful completion of post-delivery functional tests. The FGS/NIRISS was the first instrument officially accepted by NASA as part of the James Webb Space Telescope project.

As to the procurement of the four new detectors for FGS/NIRISS, the CSA and NASA agreed on cost sharing: NASA would manage the procurement with Teledyne Scientific & Imaging LLC until the detectors are completed at which point they would be procured off-the-shelf by the CSA (through PWGSC).

In , NASA initiated a cryogenic test campaign with the Integrated Science Instrument Module (ISIM). The test was completed in , and the FGS/NIRISS performed as expected.

The second cryogenic test campaign was conducted in as the integration and test activities at NASA with ISIM continued. As well, in , the FGS/NIRISS detectors were replaced after the completion of the second cryogenic test campaign.

The launch date for the James Webb telescope is currently planned for .

In , when the project obtained Treasury Board approval for the revised EPA, the anticipated mission launch date was . Following a re-planning exercise conducted by NASA, the launch date was slipped to , extending the project life by 5.5 years. There was an associated cost increase in the mission's integration and test phase, due to NASA having originally underestimated the work needed for this phase. The scope of work remaining to be completed for this project is as follows:

Although the flight instrument has now been delivered, the project is still in the implementation phase where support must be provided for the integration of the FGS/NIRISS to the spacecraft, for the launch activities and for the spacecraft commissioning activities.

With all the integration and test activities at NASA having been delayed and the duration of these activities revised under the NASA replan, the CSA and COM DEV are required to provide direct engineering post-delivery support to NASA for FGS/NIRISS and to the James Webb mission commissioning activities from up until .

Official mission operations will commence after the completion of the telescope's commissioning, six months after its launch. The James Webb telescope operations centre will be located in the Space Telescope Institute in Baltimore, Maryland, in the United States. Canadian scientists will be on location to directly support the operations of the FGS and NIRISS throughout the mission's operations. The operations will also be supported by engineering staff in order to be able to address technical issues if and when they occur to ensure the functionality of Canada's instruments.

Ultimately this remaining scope of work and the extension of the mission schedule resulted in cost increases that could not be absorbed by the project authorities. As well, PWGSC needed contractual authorities for acquiring the new detectors under a sole-source contract with a US supplier. As a result, the CSA prepared a new submission to Treasury Board addressing the issues above. The submission was approved in . Treasury Board granted a revised EPA of $169.9 million (excluding taxes).

In , NASA completed the third and final cryogenic test campaign of ISIM at NASA's GSFC. During this test campaign, the FGS/NIRISS performed as expected, thus successfully closing the final performance verification of Canada's contribution to the James Webb Space Telescope. In , NASA entered the next level of spacecraft integration and testing with the joining of ISIM and the Optical Telescope Element to form the OTIS (Optical Telescope element and Integrated Science instrument module).

In , the Integrated Science Instrument Module (ISIM) was integrated with the Optical Telescope and the new assembly (nicknamed OTIS, which stands for Optical Telescope and Science Instruments) underwent a series of rigorous environmental testing, comprised of ambient functional, vibration and acoustic testing, at NASA Goddard Space Flight Center in Maryland. The FGS/NIRISS team has supported these tests and prepared for the OTIS cryogenic tests planned for the summer of .

In the OTIS module was shipped to the NASA Johnson Space Center where it went through a series of cryogenic vacuum tests designed to ensure the telescope functioned as expected in an extremely cold, airless environment akin to that of space. These tests, which lasted about 100 days, were completed successfully in , with flawless performance from the Canadian instruments FGS and NIRISS. In the OTIS was shipped to Northrop Grumman Aerospace Systems (NGAS) in California, where it will be integrated with the spacecraft element to form the complete James Webb Telescope Observatory.

Although the OTIS module testing was completed successfully and on schedule, in the James Webb Space Telescope mission saw significant delays. On , NASA announced that the launch planned for was delayed until the spring of , due to a combination of some integration activities on the spacecraft bus and sunshield at NGAS taking longer than planned and the integration of lessons learned from earlier testing. Then, after an independent assessment of the remaining integration and test tasks, on , NASA announced a further launch delay to approximately . A more specific launch time frame will be defined by an independent review board which will provide an assessment to the US Congress in the summer of .

Date modified: